
The True Undoing of a Project: It's Not Just the Critical Path
Oct 17, 2023While the critical path is fundamental, it's not the sole factor that can derail a project. In fact, there's a two more silent saboteurs: dependencies and focus.
Consider this:
👉 A project with a straightforward, linear flow is often predictable.
👉 ... but introduce dependencies, and the complexity can quickly overshadow our ability to reason with it.
Frameworks like Kanban's work-in-progress limits or Amazon's single-threaded teams address this by emphasizing the importance of focus.
Goldratt's insight (from Critical Chain) was this:
đź’ˇ Most projects kick off by zooming in on the critical path, pouring resources to ensure smooth sailing. Simultaneously, in fear of delaying, other tasks are parallelized *too early*.
Herein lies the mistake. It diverts focus from what's truly critical.
⚡️ Instead, Goldratt suggests treating these parallel tasks as feeders, starting them "just in time + buffer" with respect to the critical path. In other words, figure out when is the absolute latest each feeder task can start, and add some buffer to it.
By doing so:
1. The critical path gets undivided attention.
2. Completed tasks don't stagnate awaiting the next step.
3. The pitfalls of multi-tasking and priority inversions (having a low priority task consume resources that should be working on a higher priority task) are avoided.
A shift in approach? Absolutely. Effective? You bet!
Don't miss a post!
New posts to your inbox.Â
We hate SPAM. We will never sell your information, for any reason. Unsubscribe anytime.